Mumbai: Kasara-Khardi third line set to ease rail congestion in Thal Ghat
Updated On: 17 April, 2026 08:18 AM IST | Mumbai | Rajendra B. Aklekar
New third track between Kalyan and Kasara spans 67 km, with partial Asangaon-Kasara section covering roughly 35 km in Phase 1

The 13.53-km stretch between Kasara and Khardi is now at the completion stage. PICS/BY SPECIAL ARRANGEMENT
Sitting at the edge of the Thal Ghat near Kasara, a small but significant piece of the rail jigsaw puzzle is finally in readiness, filling the critical gap, easing train operations, and adding some relief to the Kalyan-Kasara belt commuters.
A new 13.53-km third line between Kasara and Khardi is set to be electrified on May 12, following which the train operations will begin after statutory clearances from the Commissioner of Railway Safety (CRS). This line will be useful to segregate the suburban and mail express trains at the crucial Kasara point.