Updated On: 07 January, 2025 07:43 AM IST | Mumbai | Sameer Surve
Officials looking to complete approach road work by mid-February to finish project on time

Several deadlines set for the Gokhale bridge work have lapsed. Pics/Nimesh Dave
The BMC still has a chance to meet the deadline to complete the Gopal Krishna Gokhale Bridge work. If the civic body manages to complete the last pier on both approaches by mid-February then the project work can be completed by April-end. According to a BMC official, lowering of the girder over the railway portion has been completed. The final work of installing a pier on approach roads on both sides is pending. “If we complete this task by mid-February, we can complete work by the end of April 2025. We are hoping the task will be completed in time,” the official told mid-day.

Only work of installing the last pier on both approach roads remains