Updated On: 28 March, 2025 04:59 PM IST | Mumbai | mid-day online correspondent
Additional Municipal Commissioner (Projects) Abhijit Bangar has directed officials to adopt an 'end-to-end' approach, ensuring entire roads are completed rather than working in scattered patches

Pic/BMC
The Brihanmumbai Municipal Corporation (BMC) said that it accelerating its cement concrete road project in the Mumbai Metropolitan Region, aiming for completion by May 31, 2025. Additional Municipal Commissioner (Projects) Abhijit Bangar has directed officials to adopt an 'end-to-end' approach, ensuring entire roads are completed rather than working in scattered patches.
During his inspection of ongoing concreting works in the western suburbs, Bangar emphasised the need for micro-planning and fixing road-wise completion dates. If entire roads cannot be completed within the set timeline, he instructed that work should be finished junction-to-junction. Proper barricades must be installed to regulate traffic, and construction activities should be well-coordinated to avoid disruptions.