WR completes Phase-I of rebuilding bridge between Mahim and Bandra stations

The second phase of dismantling unserviceable abutment, rebuilding the abutment and laying tracks on proper girders is slated to complete in the month of May 2025

Listen to this article :
(Pic/WR)

(Pic/WR)

Western Railway (WR) on Monday announced the successful completion of the first phase of bridge No. 20 between Mahim and Bandra railway stations in Mumbai.

On the intervening night of January 24-25 and January 25-26, Western Railway took major blocks to rebuild the south abutment of the bridge.
 
In an official statement, the WR said, the major blocks of 9 hrs 30 mins each taken on two successive nights lead to completion of phase-I of rebuilding of the south abutment of Bridge No. 20 on the Mithi River between Mahim and Bandra stations.