Updated On: 14 October, 2024 07:49 AM IST | Mumbai | Rajendra B. Aklekar
MMRC has outlined essential upgrades and deadlines to enhance last-mile connectivity, including completed walkways and discussions with agencies

Crowds gather at the access gates inside the Aqua Line, on Day 2 of its opening on October 8. Pic/Ashish Raje
After criticism about incomplete work and last-mile connectivity issues, the Mumbai Metro Rail Corporation (MMRC) that operates the underground Aqua Line 3 issued details with deadlines, on Sunday, of what was in the works and what had been planned shortly to ease commuting.
“We have taken up Multi Modal Integration (MMI) works in coordination with all stakeholders and service providers at Aqua Line (Metro-3) stations, ensuring seamless connectivity and convenience for passengers. MMRC contractors have reinstated the road network in and around underground stations, except BKC (where major reinstatement is in progress at Income Tax junction which will be completed in six weeks),” an official said.