Updated On: 06 February, 2025 09:14 PM IST | Mumbai | mid-day online correspondent
BMC said massive repair works were also carried out simultaneously at various places, including Powai Lake, Bhandup, Maroshi, Morarji Nagar, Bandra, Vijaynagar Bridge, Sahar Village, Sahar Cargo and Dharavi

Pic/BMC
The commissioning of the new 2,400-mm diameter Tansa Channel from Powai Anchor Block to Maroshi Hydrogada (Tunnel shaft) was completed on Thursday, said Brihanmumbai Municipal Corporation (BMC).
The Mumbai civic body in an official release said 44 engineers and 200 workers have been working non-stop for 30 hours to make the water channel operational and repair works. This will help ensure that the water is supplied at the right pressure. After the water line is charged, the water supply to the areas of S, L, K East, H East, and G North zones will be smooth, BMC said.